For this critical project, the MDTA is using a progressive design-build process, which brings on board a project delivery team under one entity and a single contract to provide both design and construction services. The MDTA will work to foster collaboration among the project team, local communities, and stakeholders, ensuring open communication and inclusive partnership opportunities, particularly for small and disadvantaged businesses. The project scope of work and accelerated timeline will require a substantial amount of skilled labor to complete the construction expeditiously, safely, and reliably.
The two-phase progressive design-build process emphasizes cooperation and flexibility to adapt to emerging needs and changes. The process involves a single contract that unites MDTA with Kiewit, which includes contractor and designer roles. Kiewit was procured as a qualified team for initial services to develop the project scope and requirements in collaboration with MDTA and project stakeholders. Upon successful completion of Phase 1, Kiewit will have exclusive negotiating rights for Phase 2, which includes project final design/engineering and construction. In the event a guaranteed maximum price is not agreed upon, the MDTA will deliver the work under a separate contracting mechanism.
The MDTA Board also approved the temporary suspension of toll collection on I-695/Exit 44 turnaround until the completion of the rebuild project. The MDTA began this pilot program in May to mitigate the effect on local traffic while providing truck and commercial vehicles with direct and easy access to the Port of Baltimore, ensuring minimal disruption to surrounding communities and traffic. The MDTA recognizes this initiative will benefit customers.
In July, the Federal Highway Administration issued a Categorical Exclusion classification and National Environmental Policy Act approval for the I-695 Francis Scott Key Bridge Rebuild Project. The federal agency determined that because the replacement bridge will be within the former bridge’s right of way and have the same capacity of four travel lanes, it is not anticipated to significantly impact community, natural, or cultural resources.
Your local Bomag Americas dealer |
---|
Linder Industrial Machinery |
The MDTA released a Request for Proposals in July for the general engineering consultant, who will serve as MDTA’s engineering representative for the rebuild. The MDTA expects to award the $75 million contract in January 2025.
As design advances, the MDTA will continue to engage with Marylanders on the future of the bridge.